New Feature
Feature 1: Track cost and duration of production downtime
Impact area: Production module
Introduction: Production downtime report measures the duration and cost of downtime for a production resource, operation, and work center. Both planned and unplanned downtime are measured, and cost is calculated based on the cost per unit of time and total downtime.
Downtime is tracked from the start of an operation until the operation is completed. Downtime sums all of the snippets when operation was suspended during operational hours. Downtime considers only working hours.
Cost of planned and unplanned downtime can now be specified for a production resource.
Prerequisites:
- Set up resource production and downtime costs
- Set up suspend reasons
Functionality:
- Access report by going to Reports → Production → Production Downtime Report
More information:
Feature 2: Xero Synchronization Report
Impact area: Reports module
Introduction: During synchronization with Xero, items could be imported to Xero but ultimately have status skipped, pending, or failed. This will cause an information discrepancy between DEAR and Xero. This new report allows the user to see discrepancies where data in DEAR has not been imported to Xero.
NOTE: Payments for consolidated invoices cannot be imported to DEAR. You will need to manually apply a payment in DEAR to the imported consolidated invoice.
Prerequisites:
- Active Xero Integraion
- Financial Reporting permission
Functionality:
- Access report by going to Reports → Financials → Xero Synchronization Reports
- The report contains the following data types with Failed, Pending, Skipped, or Completed status:
- Attachments
- Contacts
- Credit notes
- Customer credits
- Invoices
- Payments (payments and refunds)
- Supplier deposit
- Manual journals
- Money tasks
- ProductsAccess report
More information: